PROMOXBUZZ FX

Promoxbuzz Natural To Street

Promoxbuzz Natural To Street

Wednesday, June 22, 2016

Earned Value Management (EVM)






Earned Value Management
What’s the Meaning of Earned Value Management?
The definition of the earned value management is a project management technique for measuring project performance and progress in the project to achieve an objective manner.  The EVM is a systematic project management process use to find the variances based on the comparison of work performance and work planned whether behind or ahead. The Cost and Schedule control can forecast the project performing. Each data is based on the time or date or scheduled progress.
The advantages of EVM are:
  • Preventing scope creep
  • Improving communication and visibility with stakeholders
  • Reducing risk
  • Profitability analysis
  • Project forecasting
  • Better accountability
  • Performance tracking
Data EVM:
  • Budget at Completion (BAC)
  • Total Cost of Project
  • Budgeted Cost for Work Scheduled (BCWS)
  • Planned Value (PV)
  • Budgeted Cost for Work Performed (BCWP)
  • Earned Value (EV)
  • Actual Cost of Work Performed (ACWP)
  • Actual Cost (AC)

Cost Forecasting as follows:
  • Estimate at Completion (EAC)
  • Estimate to Complete (ETC)

Variance as follows:
  • Cost Variances (CV)
  • Schedule Variances (SV)
  • Variance at Completion (VAC)


Performance as follows:
Cost Performance Index(CPI)
Schedule Performance Index(SPI)

Formula:

CV = BCWP – ACWP
SV = BCWP – BCWS
CPI = BCWP / ACWP
SPI = BCWP/BCWS
EAC = ACWP +ETC
ETC = (BAC – BCWP) / CPI
BAC = Original Project Estimate



Example for EXM:

The total estimated duration of the mass excavation activities in an office building project is 40 days. After 15 days the project manager receives the following information:
Type of excavation
Total Quantity (CY)
Unit Price

Total Budget
(RM)
Actual
(RM)
Actual Cost
(RM)
Common
39,000
4.52
176,500
13,200
59,700
Earth
20,000
2.50
50,000
7,800
17,950
Clay
10,000
5.50
44,000
1,200
5,850
Rock
12,000
7.50
82,500
4,200
35,900



Solution:
= Work done (day)/ Completion day = 15days/40days = 0.375
BCWS (RM) = 0.375 x 176,500 = RM 66,187.50
BCWP (RM) = Actual x Unit price = 7,800 x 2.50 = RM19,500

Activity
Common
Earth
Clay
Rock
Total
Status
Total Budget
176,500
50,000
44,000
82,500
353,000

% Complete
33.85
39.00
12.00
35.00


BCWS (RM)
66,187.50
18,750
16,500
30,938
132,376

BCWP(RM)
59,664
19,500
6,600
31,500
117,264

ACWP (RM)
59,700
17,950
5,850
35,900
119,400

SV
-6,523.50
750.00
-9,900
562.00
-15,111.50
Behind
CV
38
1,550
750.00
-4,400
-2,062
Under budget
SPI
0.90
1.04
0.400
1.02
0.84

CPI
1.11
1.086
1.13
0.88
1.024


So,
BAC = RM 353,000
ECT = (RM353,000 – RM117,264)/1.024 = RM230,211

EAC = ACWP – ETC = 119,400 – 230,211 = -RM110,811

Share this:

Post a Comment

 
Copyright © 2014 ProMoxBuzz. Designed by OddThemes