PROMOXBUZZ FX

Promoxbuzz Natural To Street

Promoxbuzz Natural To Street

Engineering

Engineering

Entertainment

Sport

Business

Business

Sunday, September 12, 2021

METHOD STATEMENT FOR DUCTILE IRON PIPE

 METHOD STATEMENT FOR DUCTILE IRON PIPE 

1               CONSTRUCTION PROCEDURES

1.1           Preparation Work 

1. The application of wayleave relaxation for the pipe will be submitted to relevant authority seeking approval (Authorities) prior to commencement of the pipe works. 

2.   Carry out the setting out of pipe route as specified in the construction drawing and within ROW, while setting out for pipe alignment will only be carried up upon approval of wayleave relaxation.  

3.   Areas where in to start permanent works shall be checked ensuring that they are ready for the said installation.  

 

1.2           Trench Excavation

a) The trench shall be excavated by such method as allowed by relevant authority and project specification for proper installation.

b) Trench excavation shall be carried out by such methods and to such lines, dimensions and depths as per required in the specification and as shown in the construction drawing to allow for the proper construction of the works.

c)   After identifying pipe crossing location, mark the alignment of pipe crossing and the alignment should approved by consultant and client.

d)   Excavate along the pipe crossing trenches to the required depth and width.

e)  Allowed to place excavated materials by the road-side. Excavated materials shall be carted away to a waiting lorry and transported to dump site if required.

f)   Certain parts of the pipeline may be laid in ground with high water table, especially in areas adjacent to the streams, river crossings and ponds. Dewatering shall be carried out to ensure excavations and trenches dry for the pipeline installation work to be carried in a safe manner during the execution of the work. 

g)   The trench bottom should be place with approved sand and well compacted by small compactor.

h) Holes or pit for pipe bells should be provided at each joint but should be no larger than necessary for joint assembly.

i)   Before jointing the pipe, the brick should placed pipe bottom and shall have 150mm spacing with bedding and bottom surface of the pipe. 

 

1.3           Preparation for Pipe jointing

a)     Before assembling the joint, the spigot of the pipe and interior of socket of the adjacent pipe shall both be thoroughly cleaned.

b)    The gasket shall be wiped clean and flexed and then placed in the socket with bulb leading. The groove in the gasket must be located on the retaining bead in the socket, and the retaining heel of the gasket firmly bedded in its seat so that the heel of the gasket is not proud of the mouth of the pipe

c)   To ensure the gasket fits evenly around the whole circumference, removing any bugles that prevent the proper entry of the spigot end

d)   A thin film of lubricant is then applied to the inside surface of the gasket which will be in contact with the entering spigot. In addition, a thin film of lubricant should be applied to the outside surface of the spigot end.

e)   The spigot of the pipe jointed must be aligned and entered carefully into the adjacent socket until it makes contact with the gasket. Final assembly of the joint is completed from this position.


 

1.4           Laying pipe 

a)   To deliver designated site numbers of Ductile iron pipe and handling properly at road shoulder to prevent any damage of pipe materials.

b)    Cleaning the internal pipe cement lining, external bitumen wrapping and also both ends of the pipe with cloth.

c)  Loading the pipe line into the trench by excavator or backhoe. The pipe should be lowered progressively into the trenches using width belt or sling. When the main is being laid downhill, for example, the pipes are occasionally laid with the bells facing uphill for ease of installation.

d)    Dig a shallow bell hole in the trench bottom, lower the pipe and make up the joint. Slide the sling to the bell end and lift slightly to provide clearance to slide the encasement to the end. Small pipe can be pushed into the bell socket with a long bar. Large pipe requires additional power, such as a jack, lever puller, or backhoe.

e)     After the pipe is lowered, it shall be laid in the line and level as specified in construction drawing.

f)     Joint assembly is completed by forcing the spigot end of the entering pipe past the gasket, which is this compressed, until the first painted strip on the end of the pipe disappear and the second painted strip is approximately flushed with the socket face.

g)  If joint is difficult to assemble, the spigot should be removed and rotated 90 degree before attempting to assemble a second time. If the joint is still difficult to assemble, the spigot should be removed and the gasket examined.




h)    At times when pipe laying is not in progress, the open ends of the pipe should be closed with a watertight plug or other means approved by consultant or client. The plug should have a means of venting and, when practical, should remain in place until the trench is pumped dry. Air or water pressure in the pipeline must be released prior to removal of the plug. Care must be taken to prevent pipe flotation if the trench floods.  

i)      The pipes body shall sit on the brick with 2 meters interval.

j)      After the new pipe line is completed, both ends capped with blank flange joint and ready to fill in water for Testing and Commissioning.

1.5           Pipe cutting

a)     Where flexible joints are to be made, the cut ends must be trimmed with a file or grinder to remove the burr formed during cutting and a chamfer must be provided.

b)  A Power Driven Abrasive Disc can be used and is suitable for all sizes. There is no need for adjustment to suit pipe size or to attach machinery to the pipe. The abrasive discs are fitted to suitable hand held power tools usually driven by compressed air or small internal combustion engines.

c)     After cutting the pipe, check the cut end and where is found to be oval, locate and mark the major axis. Measure the length of the major axis. The ovality correction is required before jointing to ensure that the cut spigot must be chamfered.

1.6           Concrete Encasement 

a)      Once all the pipes jointed and laid on ground, the formwork shall be placed the both side of pipe with 150mm cover from the edge of the pipe. 

b)    All formworks support shall be fabricating accordingly to prevent any damage or lifted of formwork during concreting. 

c)     Once fabrication of formwork completed, invite client, consultant and main contractor to inspect the works before concreting. 

d)      Pour the concrete not more than 1-meter-high to prevent any segregation of the concrete upon approved by consultant. 

e)      Formwork shall be dismantling after get 7 days of compressive test result release and satisfactory by consultant. 

f)       Upon compressive test approved and dismantling formwork, backfill the entire area with the approved fill materials. Backfilling must follow procedure of embankment filling and its appropriate testing requirements.

 

1.7           Backfilling

a)  Backfilling shall be use suitable materials or approved materials both side of concrete encasement until the subgrade level. The procedure of backfill including testing shall follow the specification requirements. 

b)   Fill materials shall be generally being placed in layer sand uniformly compacted by using plate/small compactor before the next layer is applied. Loose thickness of each layer shall not be greater than 300mm. 

c)    Special care shall be taken to properly compact backfill against the undersides of concrete encasement without disturbing or damaging the concrete encasement.  Backfill shall be built up evenly on both sides of each concrete encasement along its entire length.

d)      Backfilling shall not more than 300mm of cover has been placed and compacted. 

Note: Testing and Commissioning of the pipe after all pipe crossing (both side carriageway) is completed. The testing will refer to the Testing and Commissioning Method Statement. 

USE A PULSE OXIMETER CORRECTLY AT HOME


Use a Pulse Oximeter correctly at Home


 

In the midst of the COVID-19 emergency, specialists are encouraging patients to take measures to hold their oxygen immersion under tight restraints prior to hurrying to the clinic, guaranteeing a ton of them could be relieved in the event that they follow fitting clinical prompt while being in home disengagement. 

 

To actually take a look at oxygen immersion, COVID-19 patients can utilize a heartbeat oximeter to screen oxygen levels all alone. Be that as it may, prior to utilizing it, one should realize how to utilize it accurately.



Remember prior to utilizing an oximeter: 

 

*Rest for 10-15 mins prior to taking estimations 

 

*Rest a hand on the chest keep still 

 

*Place the oximeter on the center or forefinger 

 

*Keep it in a similar spot till the perusing is steady 

 

*Register the most noteworthy outcome once the perusing has been settled 

 

*Identify the perusing cautiously 

 

*Start recording from the pattern and record threefold per day except if you notice any progressions in your wellbeing 

 

*Consult a clinical expert if there should arise an occurrence of shortness of breath or plunge in oxygen levels to 93 percent or less

Method Statement for Testing and Commissioning DICL pipe

METHOD STATEMENT 

FOR 

TESTING AND COMMISSIONING 

DICL PIPE 




1               INTRODUCTION

1.1           Purpose

The work method statement shall describe the construction procedures, materials, plant and equipment’s required, resources needed and precautions to perform the testing and commissioning ALL size ductile iron pipes for water supply system.

The core forming vectors of the works encompasses the following:

-       Material Resources

-       Machinery & Equipment Resources

-       Testing and Commissioning Procedure 

 

1.2           Scope of work

This procedure will define the method to be used to ensure that the testing and commissioning of the pipes correctly and acceptable and shall conform to the contract document and specification. The scope of work included: 

a)     Site preparation.

b)    Sectional and Leakage Test

c)     System Test

d)    Flushing and Sterilizing 

 

2               ABBREVIATION & DEFINITIONS

Abbreviation 

Definition 

Reps.

Representative

SPW

Standard of pipe work

No.

Number

Ref.

Reference

ROW

Right of Way

Qty.

Quantity

 

3               REFERENCES

3.1           Project Documents & Construction Drawings

No.

Document

Remark

1.

Contract Specification

Technical Requirement

2.

Construction Drawing 

Overall

 

3.2           Standards

No.

Document

Remark

1.

General Specification Water Main Construction 

-

 

4               RESOURCES

4.1           Materials

Detail of materials to be used in the work:

No.

Type of Material

Qty.

CD Ref. No.

1.

500mm End Cab & Adaptor

4 nos.

-

2.

400mm End Cab & Adaptor 

4 nos.

-

3.

300mm End Cab & Adaptor 

4 nos. 

-

4.

250mm End Cab & Adaptor 

4 nos.

-

5.

200mm End Cab & Adaptor 

4 nos.

-

6.

150mm End Cab & Adaptor 

4 nos.

-

7

Meter Stand 

4 nos.

-

3.

Pressure Gauge 

2 nos.

-

4.  

Bolt and Nut 

128 nos.

-

 

4.2           Plant Machinery & Equipment 

Detail of plant and machinery proposed to be used to perform work:

No.

Plant & Machinery 

Qty.

Purpose

1.

Excavator (EX-60)

1 no.

Excavation work

2.

Backhoe 

1 no.

Excavation work

3.

Lorry (3 tons)

1 no.

For transporting the pipe materials and fitting to site

4.

Water Pump

3 nos.

For pumping water into pipe for testing and commissioning propose.

5.

Power Driven Abrasive Disc

2 nos.

To cut the Ductile Iron pipe 

           

            Detail of equipment proposed to be used to perform work:

No.

Equipments 

Qty.

Purpose

1

Scope 

2 nos.

For remove the soil on the road and digging.

2.

Hand Tools

4 sets

For tighten the bolt and nut

 

4.3           Manpower

List of supervision and workforce to be involved in the work:

No.

Description 

No of person

Role and Resposibilities

1.

Site Engineer

1

To ensure overall works implementation in order and monitor correct way of installation and pumping works 

2.

Site Supervisor

1

Coordination and Supervising site activities.

3.

Machine Operator

2

Operating the machinery.

4.

General Works 

5

To set up, jointing and tighten the bolt and nut.

 

5               TESTING AND COMMISSIONING

5.1           Preparation Work 

1.   Once the pipe completely laid underground including pipe crossing, fittings and thrust block, the location and length of the pipes to be tested shall be identify immediately. The sectional test for the pipes is not more than 1.5 km and/or from sluice valve to another sluice valve. 

2.   The once of sluice valve shall be remove and tighten the end cab with adaptor. Once end cab installed, the meter stand to be place at the end of end cab with meter stand. Pump machine shall place and connect to the meter stand. 

 

5.2            Pressure Test – Sectional and Leakage Test

a)   Testing of pipe shall be carried out in strict accordance with the specifications.

b)   The pressure gauge shall be placed at the end of the pipe (at end cab). Stop ends shall be cast iron or steel. 

c)   Pressure gauge shall have a dial not less than 150mm diameter and graduated to read up to 15 bars with 0.25 bar graduation.

d)   Pressure test should be carried first to the pressure test head of water is 90m head or 9 bars.

e)   After the pressure reach 9 bars, the pipes shall be left a night or not more than 24 hours to ensure water into the pipe absorbed in cement lining. If pressure of pipes decreased, more water shall be pumped to raise the pressure slowly to the 9 bars.

f)    The pressure shall be maintained for one (1) hours and witnesses by JBALB and consultant. 

g)   If the pressure remains within or not exceed 5% of the test pressure for hours, this indicate that there is no leakage in the system and the test section of the pipeline shall be deemed to have passed the pressure test.  

h)   The recommended maximum section of pipeline to be tested should not exceed 1500 meters maximum or from sluice valve to another sluice valve. 

i)    If leaks are discovered, depressurize the test section before repairing the leaks for 8 hours. 

j)    All defects shall be repaired and the test shall be repeated.


5.3     System Test

a)   Testing of pipe shall be carried out in strict accordance with the specifications. 

b)   Prior any test to be conducted, consultant and JBALB representatives shall be invited to inspect the pipeline, pump, pressure gauge, etc. 

c)   The required working pressure and test pressure shall also be ascertained prior to commencement of the pressure test. The water pressure test will carry out with pressure pump until 7.5 bars for duration of not less than 20 minutes.

d)   More water should be pump for into the entire pipe to raise the pressure slowly in increment of 1bar bar until 7.5 bars with a pause of one minute in each increment. 

e)   Should any appreciable drop in pressure be noted during any of this pauses the test should be stopped until the cause of the pressure drop has been investigated and rectified.

f)    The pressure test should consider passed when the pressure gauge show no more reduction once reach 7.5 bars and holding time not less than 20 minutes. The allowable of the pressure drop is 5% within time period of testing.

 

5.4       Flushing and Sterilisation of pipelines

a)       After the pressure and leakage test passes, the new pipeline will carry out the flushing and sterilisation. The section is to be thoroughly flushed to remove any debris trapped during pipe laying until the water flow shows only clean water. 

b)      The sterilizing agent to be used for the sterilization will be calcium hypochlorite (CaHCI) of 65% concentration. CaHCI solution of 20mg/l concentration (pre-mixed) will be injected into the pipe via the air valve tees at predetermined location to achieve maximum utilization. 

c)       The new pipeline shall be filled with water and CaHCI solution will then be injected. Only the clean water or treated water is allowed for this testing. 

d)      Left within 24 hours after the pipe is injected with CaHCI solution. 

e)       The water samples will be taken after 24 hours from various points, should the sample shown residual chlorine show a positive value of at least 0.2ppm (0.2mg/L) then the pipeline is considered sterilized. The process will be repeated until 0.2ppm is achieved.

f)       Every pipeline shall be tested and witnessed by consultant and JBALB representatives for the main pipeline testing. 

 

6               QUALITY ASSURANCE & QUALITY CONTROL

6.1           Inspection and Testing

1.       Implementation of QAQC works shall be in accordance to Approved Project Quality Plan and relevant quality system procedures.

2.       The quality of works shall comply with the requirements of Testing & Commissioning Manual and other relevant standard documents.

 

6.2           Work Inspection Request & Checklists

1.       The work shall be carried out using the inspection form/checklist attached in Appendix 4 to ensure the finishing quality of work shall be acceptable by the contractor, consultant and/or JBALB representative.

2.       Should there is any Non-conformity of work issued, we will respond within 7 days. Root cause shall be determined, correction of work shall be taken immediately if possible and corrective action shall be taken accordingly within agreed date. All NCR shall be closed within the agreed completion date.

 

7       APPENDICES

Appendix 1:        Testing and Commissioning Sequences

Appendix 2:        Inspection Forms and Checklist

Appendix 3:        Site Locality and Layout Plan

 

 

 

 

 

Advertisement

 
Copyright © 2014 ProMoxBuzz. Designed by OddThemes